Construction Schedule - AHC's The Shell

Post date: Jul 23, 2013 4:14:01 PM

The Shell. AHC’s general contractor, Harkins Construction, began construction work in May. Below is a brief outline of their construction schedule:

· Site excavation, sheeting and shoring in preparation for building the underground parking garage: Expected to be complete by early September 2013

· Construction of underground garage: Expected to be complete by December 2013

· Construction of the apartment complex: Vertical, structural top-out expected by the end of April 2014 and full completion of The Shell by September 2014.